Monthly Construction Update
Installation of deck utilities in sector 02. Includes storm, electrical, sanitary sewer, fire line, and water feature piping.
Structural steel at Pavilion for level one is complete.
Working on structural steel erection for the Pavilion Elevator Tower.
ONCOR Transformer Pad was poured Friday 8-30-24. Transformer to be set in place.
All underfloor MEPF rough-in is complete and inspected at the Pavilion structure.
Both grade beams for the Stage Canopy Building have been poured.
Plinths for the actual glulam beam connections will be poured soon.
Updated: September 6th 2024